Progress Update

2009 February 22
by Roj
  • South Northants Council will give notice to builders as soon as papers are signed.
  • Anticipated start late March 2009.
  • 12 week build followed by 2-3 weeks snagging.  Therefore keys should be handed over to GPC at end of June.  Anticipated opening date July 2009.

How Can I help?

We will soon require…..

  • Volunteer cleaners
  • Volunteer caretakers
  • Volunteers to work in the centre, taking bookings, setting up rooms for meetings etc
  • Volunteers to work in the coffee shop when it is launched

To find out more please call Charlie Nobbs on 01604 875188